Home
Salient Features
Overview
Alignment
Profile
KMRC SPV: Suggested Organization
Action envisaged to promote Metro travel
East-West Metro Project - Integration
Management Profile
Why Metro Rail
Tender
Project Highlights
Land Requirements
Proposed Evictions
Suggested Fare Structures
Fare Comparison
Power Demand Estimation (MVA)
Power Tariff
Technical Parameters
Projected ridership
Train operation
Estimated Cost
Proposed Funding Pattern
Project Cost Estimate(As recommended by State Govt.)
Year wise investment schedule
Operation and maintenance costs
Economic Rate of Return
Internal Rate of Return
Sensitivity Analysis
News
Career
Gallery
Contacts
Feedback
FAQ
Year wise Investment Schedule
Year
Construction Schedule
Construction Cost
2009-10
5.4%
253
2010-11
20.1%
940
2011-12
21.2%
991
2012-13
21.9%
1,024
2013-14
20.0%
1,028
2014-15
9.4%
440
Total
100.0%
4,676
* Rs. in Crores