Year wise Investment Schedule
Year Construction Schedule Construction Cost
2009-10 5.4% 253
2010-11 20.1% 940
2011-12 21.2% 991
2012-13 21.9% 1,024
2013-14 20.0% 1,028
2014-15 9.4% 440
Total 100.0% 4,676

* Rs. in Crores