Detailed Project Cost
Sl No. Item Cost estimate as recommmended by the State Govt. (Rs. in Crpres) Cost estimate as recommmended by the MOUD (Rs. in Crpres)
1 Land 126.06 126.06
2 Alignment and Formation 952.40 952.40
3 Station Buildings 945.00 126.06
4 Depot 280.00 126.06
5 P-Way 78.10 126.06
6 Traction and Power Supply 290.42 126.06
7 Signaling and Telecom 185.00 126.06
8 R & R hutments 30.00 126.06
9 Misc., utilities, road works, other civil works such as median, station signages, envtl. protection 51.375 126.06
10 Rolling Stock 554.80 126.06
11 Property development at station areas and greenery at central park depot 250.00 126.06
12 Total of all items except Land 3617.10 126.06
13 General charges @ 5% on items except land 180.85 126.06
14 Total of all items including G. Charges 3924.01 126.06
15 1% Design charges on item 14 39.24 126.06
16 Total of all items 3963.25 126.06
17 Contingencies including administrative charges @ 4% on all items 158.53 126.06
18 Gross total 4121.78 126.06
19 Provision for interim consultancy charges 5.00 126.06
20 Capital cost estimates (without taxes & duties) 4126.78 126.06
21 Taxes and Duties 441.22 126.06
22 Estimated cost (2007 prices) inclusive of taxes 4568.00 126.06
23 Interest during construction 233.00 126.06
24 Price escalation 364.00 126.06
  Total Estimated Cost (2007 prices) inclusive of all 5165.00 4676.00